Costs and Funding Sources

SOURCES of FUNDS

Expected Sources
Money Provided by School $1931
Sale of Green Tags $2000
Kansas Energy Office Support $1000
Money or Services Donated
Foundation parts & labor, steel pipe
Cost of materials: $1446 +
wire, conduit, boxes, Labor

 

PROJECT PARTS LIST (Local utility and/or local business contribution)

Listed below are some additional items that will need to be purchased in order to completely install a SkyStream 3.7 turbine.  All the wire and conduit prices will vary depending on how far it is from your turbine to the school connection.  These items will hopefully be donated by local businesses or utilities.  Note:  You will not need ALL of the items listed below.  Items will be dependent upon the choice of a 240V or 120V connection.

Additional Items for Turbine and Tower
Qty. Material Cost
2 Copper Grounding Rods (3/4") $30 each
1 Tower base fused disconnect box $118
1 School disconnect box $118
3 AWG 10 turbine electrical wire (80ft)  
300ft 120V Turbine Wire (Nacelle to tower disconnect) $214.50
300ft 240V Turbine Wire (Nacelle to tower disconnect) $296.70
Varies Steel Electrical conduit $11.20 per 10ft length
Varies PVC Schedule 40 Electrical conduit $6.53 per 10ft length
Varies Steel exterior grade electrical conduit Varies
Varies Turbine interconnection electrical wire (from tower disconnect to school) * Varies

*See Wiring Prices table below.

Below is a table listing approximate wire prices.  The prices will vary depending on how far it is from the turbine to the school.  The price also changes when using 240V versus 120V.  The price does reflect the use of a contractor and a 30% markup.

Wire Prices (installed)
Voltage Lengths Total Cost
120V 50ft to 500ft $14 - $1000
240V 50ft to 1000ft $20 - $3000

 

TURBINE COSTS (School plus green tag contribution)

The cost of the SkyStream 3.7 is described below. Included is the retail price of the turbine as well as the cost NREL has been given from the SkyStream manufacturers.

Turbine Cost Estimates
Retail Cost** $6000.00 (estimate)
Non-profit, Schools Discounted Cost $3727.00

** This is an estimated price. The actual price will vary from dealer to dealer.

TOWER AND FOUNDATION COSTS (School and/or community support contribution)

There are a couple of options regarding the style of tower for use with the SkyStream 3.7 turbine. Below is the estimated cost of each type of tower and foundation.  All the prices for materials are subject to change due to the market.  This is just an estimate for your use.

70-ft Guyed Tower & Foundation Cost Estimates (all costs are rounded)
Qty. Material Cost

Tower

1 Tower Kit (Skystream) $1032.00
1 Tower Adaptor (Skystream) $122.00
1 Lightning Protection Kit $50.00
2 3/4"x 12" Eyebolt $5.00
2 3/4"x 8" Eyebolt $5.00
- 5" Sch40 Steel Pipe $956.00 (est.)
Total Tower Cost
$2200.00

Foundation

- Concrete** $550.00
177.5 ft Rebar #3 $0.18/ft
137.5 ft Rebar #4 $0.28/ft
20 ft Rebar #6 $0.63/ft
Total Foundation Cost
$633.00

Totals

Grand Total for Guyed Tower
$2650.00

 

60-ft Monopole & Foundation Cost Estimates (all costs are rounded)
Qty. Material Cost

Table

1 60-ft Monopole Tower $8411.00
1 Lightning Protection Kit $50.00
Total Monopole Cost
$8461.00

Foundation

6.00 Concrete(cubic yards) $523.60
198.80 Rebar #4(ft) $53.08
115.00 Rebar #8(ft) $123.05
1 Foundation Bolt Kit $363.00
Total Foundation Cost
$1062.73

Totals

Grand Total for Monopole
$9523.73

 

45-ft Monopole & Foundation Cost Estimates (all costs are rounded)
Qty. Material Cost

Tower

1 45-ft Monopole Tower $3214.00
1 Lightning Protection Kit $50.00
1 Gin Pole Kit (dealer purch.) -
Total Monopole Cost
$3264.00

Foundation

6.00 Concrete(cubic yards) $479.97
182.23 Rebar #4(ft) $48.66
105.00 Rebar #8(ft) $112.35
1 Hinge Plate Kit $327.00
1 Foundation Bolt Kit $363.00
Total Foundation Cost
$1330.97

Totals

Grand Total for Monopole
$5071.97

 

33.5/34-ft Monopole & Foundation Cost Estimates (all costs are rounded)
Qty. Material Cost

Tower

1 Monopole Tower $2978.00
1 Lightning Protection Kit $50.00
1 Gin Pole Kit (dealer purch.) $419.00
Total Monopole Cost
$3028.00

Foundation

12.00 Concrete(cubic yards) $960.00
0.00 Rebar #4(ft) -
216.00 Rebar #6(ft) $129.60
0.00 Rebar #7(ft)

-

1 Hinge Plate Kit $203.00
1 Foundation Bolt Kit $363.00
Total Foundadtion Cost
$1655.60

Totals

Grand Total for Monopole
$4673.60

 

SMarT Foundation Cost Estimates (all costs are rounded) Replaces rebar and concrete costs for all options above except guyed tower
Item Cost when design
wind speed <110
Cost when design
wind speed <150
Tower $3776.00 $3776.00
SMarT Foundation Kit $635.00 $635.00
Concrete $285.79 $425.31
Gin Pole (n/a requires crane) - -
Hinge Plate Kit (n/a requires crane) - -
Grand Total
$4696.79
$4836.31

 

ADDITIONAL EQUIPMENT COSTS (Local utility and/or local business contribution)

There may be some additional costs to install the turbine initially. This includes rental of trenching and digging equipment and also the use of a licensed electrician. As with other prices this is just an estimate.

Additional Equipment Costs
Trencher $150/day
Electrician $30/hour